About the Project
In an ongoing effort to provide quality wireless service, both Verizon Wireless and AT&T have identified your community as one that will benefit from improved network coverage.
Milestone Towers is proposing a wireless telecommunications facility at the Stafford Right Of Way (ROW) or the junction of Interstate 95 and Route 1.
The proposal is for a 165-foot monopole and will include ground equipment required to operate the facility.
This equipment will be located at the base of the structure in a secure fenced area. Verizon Wireless and AT&T will be the first wireless carriers to locate on the proposed tower.
Update # 3: Milestone Towers will go before the Planning Commission on Wednesday, April 24th at 6:00pm.
Update #2: Please click here to view the online Town Hall presentation held on Thursday, December 14th.
Update #1: Online Town Hall: On Thursday, December 14th @ 6:00 pm we will hold an online Town Hall webinar consisting of a short presentation followed by a question and answer time. Registration is required and can be completed on the Town Hall page.
Our Process
1. Due Diligence
Survey, FAA, FCC, NEPA, Phase 1, Geotechnical Analysis.
2. Land Use
Comprehensive Plan Application, Community Meeting, Staff Review, Planning Commission.
3. Permitting
Conduct Bid Walk With Contractors, Obtain Land Use Permit from VDOT.
4. Construction
Tower construction = 4-6 weeks | Carrier construction = 4-6 weeks on average
On-site supervision by Construction Manager.
5. Site Maintenance
Four visits per year for site maintenance | Remove trash, debris, check signage.
2-4 visits per year for carrier modifications.